From Monday until probably 29 October 2027, Heinrich-Beck-Straße will be fully closed in sections between Barbarossastraße and Reichsstraße/Stephanplatz. The reason for this is extensive civil engineering work.
While the waste disposal company of the city of Chemnitz is responsible for the renovation of the sewerage system, eins energie in sachsen is responsible for the renewal of the drinking water pipeline and the expansion of the district heating network. At the same time, the City of Chemnitz's traffic and civil engineering department is commissioning the renewal of the road drainage systems.
Pedestrian traffic will be guided safely past the construction site at all times. Access to neighbouring properties will be ensured with restrictions. The diversion will be signposted and access to neighbouring properties and facilities will be subject to the progress of construction work and the location of the construction site/excavations in accordance with the signposting.
Krause & Co Hoch-, Tief- und Anlagenbau from Neukirchen is carrying out the construction work with a total value of around 2.1 million euros.