Expansion 2.0: Cluster East
This is a schematic representation of the current building lots. It is not possible to derive eligible addresses from the illustration. The City of Chemnitz is under no obligation to develop all addresses within the subsidised areas or construction areas.
| Start of construction: | October 2025 |
| Planned completion date: | December 2029 |
| Number of properties to be connected: | 4.154 |
| Estimated total cost: | €46.94 million |
| Estimated funding (federal/state): | €42.25 million |
| Estimated own funds from the City of Chemnitz: | €4.69 million |
| Operator / Lessee: | eins energie in sachsen GmbH & Co. KG |
| Planned start of lease: | 1 January 2030 |
| Planned end of lease: | 3112 December 2036 |
| Technology used: | FTTB |
| Service speed (target): | at least 1,000 Mbit/s |
Progress of the building works
Explanatory notes on the construction progress tables:
Construction completed
Refers to network distribution areas in which domestic connections have already been installed. Completion of construction does not yet mean the network is operational, as work may still be required on the upstream network. Operational (sub-)areas will be published separately upon completion.
Operational
The relevant network distribution area has been approved by the City of Chemnitz. This means that both the civil engineering works and the installation of the fibre-optic cables up to the fibre-optic termination point have been completed. The next stage involves the installation of the in-building fibre-optic cabling by contractors commissioned by eins energie in sachsen GmbH & Co. This may take several weeks. Individual customer activations are possible at any time once the roll-out of network level 4 has been completed for the relevant address.
in operation
The entire network distribution area is now operational, and individual customer activations can take place depending on the progress of the in-building fibre-optic cabling by eins energie in sachsen GmbH & Co. GmbH. Further information on availability can be found at www.eins.de.
| Planning | Under construction | Construction completed | Operational | in operation | |
|---|---|---|---|---|---|
| Point of Presence 14 | |||||
| Network distribution point 14.2 Adalbert-Stifter-Weg; On the Riesa railway line; Further Höhe; Glösaer Straße | in planning | ||||
| Network distribution point 14.6 Am Schnellen Markt; Frankenberger Straße; Herwehgstraße; Lichtenwalder Straße | in planning | ||||
| Distribution substation 14.9 Ebersdorfer Straße; Frankenberger Straße; Krügerstraße | in planning | ||||
| Distribution substation 14.11 Agricolastraße; Frankenberger Straße; Glösaer Straße; Huttenstraße; Lichtenwalder Straße | in planning | ||||
| Point of Presence 15 | |||||
| Network distribution point 15.9 Eberhardtsteig; Mittweidaer Straße; Silchstraße | in planning | ||||
| Network distribution point 15.12 Mittweidaer Straße | In planning | ||||
| Distribution substation 15.13 Mittweidaer Straße | in planning | ||||
| Distribution substation 15.16 Mittweidaerstraße; Ortelsdorfer Straße | in planning | ||||
| Distribution substation 15.17 Ortelsdorfer Straße | in planning | ||||
| Network distribution point 15.18 Ebersdorfer Höhe; Frankenberger Straße | in planning | ||||
| Distribution substation 15.19 Max-Saupe-Straße | Planned | Under construction | |||
| Network distribution point 15.20 On the Riesa railway line; Tännichtleite | in planning | under construction | |||
| Network distribution point 15.21 At the bend; On the Riesa railway line; Stiftsweg | in planning | under construction | |||
| Network distribution point 15.22 At the bend; Stiftsweg | in planning | under construction |
| Planning | Under construction | Construction completed | Operational | in operation | |
|---|---|---|---|---|---|
| Point of Presence 13 | |||||
| Network distribution point 13.1 Blankenauer Straße; Chemnitztalstraße | in planning | ||||
| Point of Presence 16 | |||||
| Network distribution point 16.1 Emilienstraße; Frankenberger Straße | in planning | ||||
| Distribution substation 16.2 On the Riesa railway line | in planning | ||||
| Network distribution point 16.3 Dresdner Straße: Forststraße; Hohlweg | in planning | ||||
| Distribution substation 16.4 August-Bebel-Straße; Dresdner Straße; Palmstraße; Thomas-Mann-Platz | in planning | ||||
| Network distribution point 16.5 Dresdner Straße; Forststraße; Gellertstraße; Hainstraße; Palmstraße; Zietenstraße | in planning | ||||
| Distribution substation 16.6 Heinrich-Schütz-Straße; Hofer Straße; Paul-Gerhardt-Straße; Planitzwiese | in planning |
| Planning | Under construction | Construction completed | Operational | in operation | |
|---|---|---|---|---|---|
| Point of Presence 6 | |||||
| Network distribution point 6.1 Main road | in planning | ||||
| Point of Presence 7 | |||||
| Network distribution centre 7.3 Hugo-Pöschmann-Straße | in planning | ||||
| Distribution substation 7.6 Mittagleite | in planning | ||||
| Network distribution point 7.20 Marktsteig, Mittagleite | in planning | under construction | |||
| Point of Presence 18 | |||||
| Network distribution area 18.1 Eubaer Straße | in planning | ||||
| Distribution area 18.3 Augustusburger Straße, Eubaer Straße | In planning | ||||
| Distribution substation area 18.3 Augustusburger Straße, Eubaer Straße | In planning | ||||
| Distribution area 18.5 Olbersdorfer Straße | in planning | ||||
| Distribution substation area 18.10 Adelsbergstraße | in planning | ||||
| Network distribution area 18.17 Dreiserstraße | in planning | ||||
| Network distribution area 18.19 Reinhard-Uhlig-Straße | in planning | ||||
| Distribution area 18.21 Cervantesstraße | in planning | ||||
| Distribution substation area 18.23 Cervantesstraße | in planning | ||||
| Point of Presence 19 | |||||
| Network distribution area 19.2 Dreiserstraße, Georgistraße | in planning | ||||
| Distribution substation area 19.6 Georgistraße | in planning | ||||
| Network distribution area 19.7 Barbussestraße, Kleiner Weg, Otto-Thörner-Straße | in planning | ||||
| Distribution area 19.8 Adelsbergstraße, Breitenlehn, Kirchwinkel | in planning | ||||
| Distribution substation area 19.10 Adelsbergweg, Breitenlehn | in planning | ||||
| Distribution substation area 19.11 Adelsbergstraße | in planning | ||||
| Distribution network area 19.12 Adelsbergstraße; Hermersdorfer Straße; Kleinolbersdorfer Straße | in planning | ||||
| Distribution network area 19.13 Am Schösserholz | In planning | Under construction | |||
| Distribution substation area 19.14 Am Schösserholz | in planning | ||||
| Network distribution area 19.31 Spürweg | in planning | ||||
| Point of Presence 20 | |||||
| Network distribution area 20.4 Marktsteig, Richterweg | in planning | ||||
| Distribution area 20.11 Gornauer Straße | in planning | under construction | construction completed | ||
| Network distribution area 20.12 Gornauer Straße | in planning | ||||
| Network distribution area 20.13 Reichenhainer Mühlberg | in planning | ||||
| Distribution area 20.14 Reichenhainer Mühlberg | in planning | under construction | construction completed | ||
| Distribution substation area 20.15 Reichenhainer Mühlberg | in planning | under construction | |||
| Distribution substation area 20.17 Erfenschlager Straße | in planning | ||||
| Distribution substation area 20.21 Sayder Straße | in planning | under construction |
| Planning | Under construction | Construction completed | Operational | in operation | |
|---|---|---|---|---|---|
| Point of Presence 9 | |||||
| Network distribution point 9.5 Zum Spitzberg; Altenhainer Dorfstraße | in planning | ||||
| Point of Presence 22 | |||||
| Network distribution point 22.1 Bernhard-Kuhnt-Weg; Schöne Aussicht; Zschopauer Straße | in planning | under construction | |||
| Network distribution point 22.2 Bernhard-Kuhnt-Weg; Lehmgrubenweg; Max-Brand-Straße | in planning | under construction | |||
| Network distribution point 22.3 Am Gehege; Gartenstadt | in planning | ||||
| Distribution substation 22.6 Ferdinandstraße; Schillerstraße | in planning | ||||
| Distribution substation 22.14 Am Finsterbusch; Ferdinandstraße | in planning | ||||
| Distribution substation 22.15 Ferdinandstraße | in planning | ||||
| Distribution substation 22.16 Shakespearstraße; Zschopauer Straße | in planning | ||||
| Distribution substation 22.18 Altenhainer Dorfstraße; Zschopauer Straße | in planning | ||||
| Distribution substation 22.20 Einsiedler Weg; Zschopauer Straße | in planning | under construction | |||
| Distribution substation 22.21 Altenhainer Dorfstraße; Am Winkel; Einsiedler Weg | in planning | ||||
| Distribution substation 22.22 Altenhainer Dorfstraße; Baumeister-Uhlig-Straße | in planning | ||||
| Network distribution point 22.23 Altenhainer Dorfstraße; Zum Spitzberg | in planning |
| Planning | Under construction | Construction completed | Operational | in operation | |
|---|---|---|---|---|---|
| Point of Presence 1 | |||||
| Network distribution point 1.2 Untere Hauptstraße; Waldweg | in planning | ||||
| Distribution substation 1.16 Upper Main Street | in planning | ||||
| Distribution substation 1.28 Querweg | in planning | ||||
| Point of Presence 49 | |||||
| Network distribution point 49.1 Bornaer Straße; Sandstraße | in planning | ||||
| Distribution substation 49.2 Auerswalder Straße; Bornaer Straße | planned | ||||
| Distribution substation 49.3 Auerswalder Straße; Hermann-Löns-Straße | in planning | ||||
| Distribution substation 49.5 Damaschkestraße; Hermann-Löns-Straße | in planning | under construction | |||
| Network distribution point 49.6 Bornaer Straße; Damaschkestraße; Heinersdorfer Straße | In planning | ||||
| Distribution substation 49.7 An der Hofewiese; Blankenburgstraße; Bornaer Straße | planned | ||||
| Distribution substation 49.8 Bornaer Straße; Sandstraße | in planning | ||||
| Distribution substation 49.9 In der Delle; Draisdorfer Straße; Blankenburgstraße | in planning | under construction | |||
| Distribution board 49.10 Draisdorfer Straße; Zu den Pappeln | in planning | under construction | |||
| Distribution board 49.11 Draisdorfer Straße; In der Delle | in planning | ||||
| Network distribution point 49.12 Blankenburgstraße; Draisdorfer Straße | in planning | ||||
| Distribution substation 49.13 Glücksberg; In der Delle | in planning | under construction | |||
| Distribution substation 49.14 Glücksberg; In der Delle | in planning | ||||
| Point of Presence 50 | |||||
| Network distribution point 50.1 Am Bahrehang | in planning | under construction | |||
| Distribution substation 50.2 Heinersdorfer Straße | in planning | ||||
| Distribution substation 50.3 Am Bahrebach; Heinersdorfer Straße | in planning | ||||
| Distribution substation 50.6 Am Bahrehang; Zum Kornweg | in planning | ||||
| Distribution substation 50.7 Am Bahrehang | in planning | under construction | |||
| Point of Presence 51 | |||||
| Network distribution point 51.1 Chemnitztalstraße | in planning | ||||
| Point of Presence 52 | |||||
| Network distribution point 52.2 Chemnitztalstraße; Untere Hauptstraße; Waldweg 1 | in planning |